Quality

Work is executed to the applicable project requirements, specifications, governing codes and OEM requirements, and every step is recorded against the unit's serial number.

Governing codes The fourteen gates

Valves, gauges and control panel on a J2B skid

Built to the governing code

J2B designs and manufactures each system to the applicable governing code and project basis. The service, the installation and the owner's requirements determine which code governs.

Power pipingASME B31.1Piping in power generating stations, industrial plants and central heating and cooling systems.
Process pipingASME B31.3Piping in process facilities, including chemical, petroleum and gas-handling service.
Refrigeration pipingASME B31.5Where applicable. Refrigerant and secondary coolant piping and heat transfer components.
Building services pipingASME B31.9Where applicable. Building services piping within the code's pressure, temperature and size limits.

Quality built into every unit

From qualified procedures to the turnover package, each unit carries the record of how it was built and tested.

01

Qualified welding

Qualified welding procedures, with each joint assigned a welder qualified to its procedure.

02

Material traceability

Pressure-retaining material traced to its mill test report and heat number.

03

Inspection

Fit-up, dimensional and in-process inspection at defined points in the build.

04

NDE where required

Nondestructive examination to the extent the code and the project require.

05

Pressure and functional testing

Hydrostatic or pneumatic testing, loop checks and functional tests.

06

Factory Acceptance Testing

FAT to an approved procedure, witnessed as the customer specifies.

07

Documentation and turnover

A Manufacturing Record Book and turnover package for every unit.

08

Hazardous-area construction

Class I, Division 1 and Class I, Division 2 construction as the project requires.

Hazardous-area construction

Electrical construction for Class I, Division 1 and Class I, Division 2 locations, depending on project requirements. The project's area classification sets the enclosures, instruments, wiring methods and seals.

ClassificationTypical condition
Class I, Division 1Locations where ignitable concentrations of flammable gases or vapors can exist under normal operating conditions
Class I, Division 2Locations where flammable gases or vapors are normally confined and can escape only under abnormal conditions

Materials for service life

Process piping, fittings, flanges, valves and instrumentation tubing in stainless steel, including 316 stainless where specified or required. Structural skid frames are typically hot-dip galvanized unless the customer specification requires another material or coating.

01Long lifeMaterials and finishes selected for the service and the installed environment.
02Corrosion resistanceStainless process piping and galvanized structure for exposed and corrosive service.
03MaintainabilityAccess, isolation and change-out planned into the package layout.
04ReliabilityTested assemblies built from traceable, specified materials.

From material receipt to shipping release

Each gate produces a record tied to the serial number. Hold points, marked in red, stop production until the inspection is complete and accepted.

01

Material receipt

Receiving

Incoming material checked against the purchase order, quantity and condition.

RecordReceiving report
02

Material verification

Inspection

Grade, size, schedule and markings verified against the specification.

RecordVerification record
03

MTR / heat traceability

Hold point

Mill test reports reviewed; heat numbers transferred and logged for pressure-retaining material.

RecordMTR file and heat log
04

Controlled drawings

Document control

Only released drawings at the current revision reach the floor.

RecordDrawing register
05

WPS / qualified welding

Qualification

Each joint assigned a qualified procedure and a welder qualified to it.

RecordWPS, PQR, WPQ
06

Fit-up inspection

Inspection

Alignment, gap, bevel and dimensions checked before welding begins.

RecordFit-up report
07

Welding

Production

Welds made to the assigned WPS and recorded on the weld map by welder ID.

RecordWeld map
08

NDE

Hold point

Nondestructive examination performed to the code and project extent.

RecordNDE reports
09

Pressure testing

Hold point

Hydrostatic or pneumatic test at the required pressure and hold time.

RecordTest record and chart
10

Instrument verification

Inspection

Instruments checked against the index for tag, range, calibration and installation.

RecordInstrument check sheets
11

Electrical / controls verification

Inspection

Wiring, terminations, grounding and loop checks verified end to end.

RecordLoop check records
12

FAT

Hold point

Factory Acceptance Test run to the approved procedure, witnessed as specified.

RecordSigned FAT report
13

Manufacturing Record Book

Document control

All records compiled and reviewed against the serial number.

RecordManufacturing Record Book
14

Shipping release

Hold point

Final inspection, preservation and release authorization before the unit leaves.

RecordRelease certificate
J2B Industrial
Model
Fuel gas conditioning skid
Serial no.
Assigned at start of build
Design basis
Released drawing revision
Materials
Traced to MTR and heat number
Testing
Hydrostatic and FAT, signed

Stainless nameplate, one per unit

The Manufacturing Record Book

Issued per serial number: the complete quality history of the unit.

  1. Certificate of conformance
  2. As-built drawings at released revision
  3. Material test reports and heat log
  4. Weld map, WPS, PQR and welder qualifications
  5. Fit-up and dimensional reports
  6. NDE reports
  7. Pressure test records
  8. Instrument and calibration data
  9. Electrical and loop check records
  10. FAT report and punch list closure
  11. Deviations and approved changes
  12. Shipping release and preservation

System controls

Contract and specification reviewRequirements captured before engineering begins
Supplier qualificationApproved sources for pressure parts and critical components
Inspection and test plansHold and witness points agreed with the customer
Dimensional verificationCritical interfaces checked before assembly and before shipment
Nonconformance controlDeviations recorded, dispositioned and closed
Calibrated equipmentGauges and test instruments under calibration control
Functional testingControls, shutdowns and alarms proven before FAT
Final documentationTurnover package complete at shipping release
Valves, instrumentation and control panel on a fuel gas skid

Let's build your next program.

Whether you are developing a single installation or planning a fleet deployment, J2B Industrial can work with your team to develop an engineered, manufacturable solution and establish the production capacity required to support your schedule.

Or call (904) 574-8919 · sales@j2bindustrial.com

Design basis or specification ready? Send your design basis

Program size

Sends the request to J2B Industrial. See the Privacy Policy.